Skip to content
Rallybid

Open9 days left

PRO005166 - ORiW - Design and Integration Partner

United Utilities Water Limited is looking for a supplier for "PRO005166 - ORiW - Design and Integration Partner". The estimated value is £720,000,000. Bids close on 30 November 2026 at 14:00.

Can I bid for this?

Make a free account to see how this tender fits your business and what it asks for.

Where and how to bid

  • The notice is published on Find a Tender; the buyer's documents say where bids go in. Open Find a Tender
  • Questions to the buyer close 17 November 2026 at 14:00
  • Submit by 30 November 2026 at 14:00

What the buyer says about submitting: https://uk.eu-supply.com/app/rfq/rwlentrance_s.asp?PID=109426&TID100114470&B=

What is this tender, in plain English?

United Utilities is looking for a partner to design and integrate a large project called 'Only Rainwater into Windermere' (ORiW). This project aims to improve Windermere lake's water quality by removing pollution from public and private sources, including roads. The chosen partner will help develop the project from its early design stages through to getting all the necessary approvals.

What does the buyer ask for?

  • Capable and experienced in coordinating and integrating all elements of the ORiW system and related activities.
  • Able to lead the overall delivery strategy.
  • Able to manage interfaces across the programme.
  • Able to maintain design consistency.
  • Able to ensure the solution meets requirements for necessary approvals and consents.

Who is this a good fit for?

This opportunity is suitable for businesses with significant experience in design, integration, and project management for major engineering and construction projects, especially those involving environmental improvements and wastewater infrastructure.

Written by AI from the notice. Check the original before you bid. The notice in full

Why could this be a fast result?

Nothing marks this out as a quick one: check the value, the deadline and how you bid.

What do past awards say about tenders like this?

  • Tenders like this drew about 80.2 bids each (167 awards gave a count).
  • Half of similar contracts were awarded between £70,000 and £600,000; the middle one was £186,988.

Based on 903 awards in the last 36 months: same trade, same region. Confidence: good. This describes the past; it does not predict a result. Award data

The notice in full

This notice relates to tender activity for the provision of certain design and integration services, as explained below. United Utilities Water Limited (UU) proposes to deliver a programme titled Only Rainwater into Windermere (ORiW), with the ambition to make Windermere the cleanest lake in England by removing discharges from both public and private sources, while also addressing highway runoff. This is a long-term, transformational programme designed to protect the lake's ecology, water quality and amenity value for future generations. The target end state is "Only Rainwater into Windermere", restoring the lake as close as possible to its natural condition and reducing the risk of harmful algal blooms and chemicals. The programme will deliver resilient wastewater infrastructure that supports communities, businesses and the wider National Park, while creating a potential blueprint for freshwater restoration across England. This Scope of Requirements does not include agricultural impacts; these are being considered by other programmes. A coalition has been established to develop and deliver the ORiW feasibility phase. It brings together key stakeholders, including UU, local authorities, regulators and environmental organisations, to provide strategic direction and has sponsored the commission of a ‘feasibility study’ to ascertain the art of the possible for achieving ORiW. Through the commission there are now feasible options for achieving the ambition, to improve water quality, and enhance the environmental resilience of the Windermere catchment, through a proposed ORiW system and wider infrastructure. The proposed ORiW system is made up of multiple workstreams; • First Time Sewerage (FTS), connecting properties to the public sewer network that are currently outside of the network and have never previously been connected to it. • First time Treatment (FTT), for the sites where FTS is not possible, a remote treatment solution will be implemented. • Reduced weather dependent flow, surface water management and management and treatment of highways runoff through the use of nature- based solutions where possible across the catchment. • Construction of tunnel, sewers, rising mains and associated infrastructure. • Upgrade of an existing wastewater treatment works and discharge point. UU anticipates that the ORiW system and the other strategic wastewater transfer and treatment infrastructure required for the ORiW programme (including the tunnel, rising mains, pumping stations, wastewater treatment facilities, associated drainage works and all ancillary infrastructure), will be promoted through a Development Consent Order (DCO) as a Nationally Significant Infrastructure Project (NSIP), subject to Section 35 approval by Defra. [SM1.1][WD1.2] UU are launching a competitive tendering procedure for the appointment of a Design and Integration Partner (D&IP) who will be responsible for supporting the next phase of this programme, designing the ORiW system, including whole system integration, to achieve the programme vision. UU requires the D&IP to complete feasibility, outline design, constructability and other related activities to obtain the necessary approvals and consents for the programme to proceed to the delivery phase for the preferred solution. Accordingly, the D&IP will also be responsible for the delivery of the DCO and planning approvals. As such, the outline design needs to fully support and integrate with the DCO, Town and Country Planning Act (TCPA) and land acquisition and access processes. At a high level, the initial scope of requirements for the D&IP will include, but may not be limited to the following activities across each of the workstreams of the ORiW system; • Outline Design • Planning, Consents and Land • Environmental Impact Assessments (EIA) and surveys • Stakeholder and Customer Engagement • Land Agency, Referencing and Surveying • Preparation and submission of planning applications and all supporting information • Preparation and submission of the DCO and all supporting information • Site Investigation (SI) • Early Contractor involvement (ECI) • Supporting UU in meeting reporting requirements with Ofwat i.e. PR29 Price Review • Supporting UU with any required preparation, development and submission of information for the Water Industry National Environment Programme (WINEP) and Drainage and Wastewater Management Plan (DWMP) UU require a D&IP who has the capability and experience to ensure coordination over integration of all elements of the ORiW system and all other related activities that are required. The D&IP will also need to be capable of leading the overall delivery strategy, managing interfaces across the programme, maintaining design consistency, and ensuring that the complete solution meets the requirements to obtain the necessary approvals and consents. UU is continuing to consider its approach to the delivery phase of the programme and anticipates that it may need ongoing support from the D&IP into the delivery phase to provide continuity throughout the programme lifecycle. The precise form that this ongoing support may take will be dependent on the precise delivery model that UU adopt for the delivery phase, but the role to be played by the D&IP may include typical professional services support of the nature to be expected of a design and integration professional services consultant acting for a client in relation to the delivery phase of a major engineering and construction project, for example (without limitation) either: • The D&IP acting as system integrator and detailed design partner to either UU and/or any prime contractor engaged in relation to the programme. • The D&IP acting as a system integrator partner to provide support across different workstreams and work packages forming part of the programme so that the overall programme is delivered as seamlessly as possible. • Providing alternative services to support UU’s client-side management of delivery partners engaged to undertake the delivery phase of the programme. From a contractual perspective, this may entail: • Continuing consultancy services (e.g. oversight of delivery contractors or supporting the coordination between delivery contractors and/or developing the detail of design work undertaken during the development phase) provided by the D&IP on the same, or similar, call-off contract terms and conditions as are prescribed under the framework agreement for the development phase of the Programme; or • An evolution of the delivery model and associated call-off terms and conditions envisaged under the framework agreement for the development phase of the Programme to align to the Client’s proposed delivery model for the delivery phase of the Programme, including for example: o requiring the D&IP to enter into a strategic sub-contract with one or more delivery contractors appointed by the Client for the provision of detailed design services; or o the provision by the D&IP of design and integration services to the Client as part of an integrated “Enterprise” delivery model incorporating the Client, D&IP and delivery contractors and designed to create aligned incentives across all such participants. An outline of the potential structure and commercial proposition of this Enterprise model, including the call-off contract terms and conditions that could be used to effect it, will be set out in the framework agreement on an indicative basis (recognising that the precise terms and conditions of any call-off contract and the model more broadly would be developed separately by UU and refined through engagement with other potential Enterprise participants). Whatever model is adopted, the Client will ensure that the balance of risk and reward, and the potential commercial and financial impact on the D&IP, is similar and broadly equivalent to the balance struck in the call-off terms and conditions for the development phase. This means that UU will endeavour to ensure that, as and when any call-off terms and conditions are entered into, the D&IP would not be materially better off under the enterprise or alliance type model, in all material respects, compared to the position under a continuation of the development phase arrangements. Anticipated value of each role; • Design & Integration Partner (pre delivery phase) > 4 years = circa £60-100m • System Integrator Partner (during delivery phase) > up to a further 9 years in increments at UUs discretion = circa £100m (subject to CPIH) • System Integrator and Detailed Design Partner (during delivery phase) > up to a further 9 years in increments at UUs discretion = circa £500m (subject to CPIH) Please note that the total value is given as a range (£60m to £600m) which includes the minimum and maximum total estimated values across those roles. As explained above, the system integrator partner (during delivery phase) and system integrator and detailed design partner roles are alternatives and so the combined value of each is not included in the total (only the higher of the two).

Documents

Get these tenders by email

One email a day with new tenders for the trade and area you choose. No account or password needed.

We first email you a link to confirm. Nothing else is sent until you use it. Privacy notice

Quick answers

When is the deadline for this tender?

Bids close on 30 November 2026 at 14:00.

How much is this contract worth?

The buyer estimates £720,000,000.

Who is the buyer?

The buyer is United Utilities Water Limited.

How do I bid for it?

You bid on the buyer's own portal, linked from the official notice on Find a Tender. Rallybid helps you find and prepare; a person always submits.

Where do I send my bid?

The notice does not name a portal. The buyer's tender documents say where and how to submit.

When do questions to the buyer close?

Questions (clarifications) to the buyer close 17 November 2026 at 14:00.

How many businesses usually bid for a tender like this?

Tenders like this drew about 80.2 bids each (167 awards gave a count). Based on 903 awards in the last 36 months: same trade, same region. Confidence: good. This describes the past; it does not predict a result.

Similar open tenders