Manchester International Airport Phase 2 - Overbridge Civils

Kier Transportation - CP7 NWC published this tender for "Manchester International Airport Phase 2 - Overbridge Civils". It is now closed to new bids.

This tender is closed to new bids. Similar open tenders

What is this tender, in plain English?

This tender is for civil engineering work to build a bridge structure and related road infrastructure at Manchester International Airport. It's part of a bigger project to improve train services and capacity at the airport station, allowing for longer trains.

What does the buyer ask for?

  • Install client-supplied precast bridge parts like cills, beams, and side walls.
  • Modify existing bridge cills.
  • Supply and install bridge bearing plates.
  • Build pile caps/infill.
  • Construct a reinforced concrete bridge deck slab and parapet walls.
  • Complete highway works, but not the final road surfacing.

Who is this a good fit for?

This opportunity is suitable for civil engineering contractors with experience in bridge construction and related highway infrastructure.

Written by AI from the notice. Check the original before you bid. The notice in full

What do past awards say about tenders like this?

  • Tenders like this drew about 2.6 bids each (7 awards gave a count).
  • Half of similar contracts were awarded between £574,671 and £1,141,484; the middle one was £719,640.

Based on 40 awards in the last 36 months: same trade, same region, similar value. Confidence: good. This describes the past; it does not predict a result. Award data

Who won this tender and for how much?

No award has been published for this tender yet.

The notice in full

The planned introduction of longer train services to the Airport in response to future demand growth will mean that double stacking arrangements of trains as currently used will no longer be viable. Through the project's Delivery Steering Group, Northern and TransPennine Express have carried out analysis which has identified that additional platform capacity is needed at the airport in order to realise the full benefit of longer train services serving the airport. The scheme is part of a package of proposed measures in the Manchester area that are being designed/planned to boost capacity and resilience, emanating from the Cross Manchester Capacity and Reliability Improvement Study. Improving the operation of train services in the centre of Manchester and providing further capacity at Manchester Airport station, aligns with the strategic aims of Network Rail, TfGM, TfN and the wider industry. This project in in Tranche 1 of the Manchester and North West Transformation Programme (MNTP): A remodelling of the station at Manchester Airport, specifically a platform addition or extension of multiple platforms, or provision of a new turnback facility, will be essential to accommodate the planned implementation of longer rolling stock services. The redevelopment of these platforms will enable permissive working of two 6x24m (144m) trains, in two of the four platforms at the Airport Station. This will allow for the unaltered retention of all existing TOC services both originating and terminating at the Airport Station under 'double-stacking' conditions. The works comprise the construction and completion of the bridge structure and associated highway infrastructure, including: • Installation of client-supplied precast bridge components, including cills, beams and side walls, together with associated shear key reinforcement and grout connections. • Modification of existing bridge cill. • Supply and installation of bridge bearing plates, including associated screed works. • Construction of pile caps/infill. • Placement of in-situ concrete shear key infill. • Construction of the reinforced concrete bridge deck slab. • Construction of reinforced concrete parapet walls. • Placement of in-situ concrete footpaths and fill areas. • Construction of pilasters, including reinforced concrete and brickwork elements. • Supply and installation of parapet and pilaster copings. • Construction of associated fencing, signage and PCC retaining wall. • Installation of associated ducting works. • Completion of highway works excluding final road surfacing. • Application of bridge waterproofing systems, installation of expansion joints, and completion of associated sealing and mastic works. • Construction of associated drainage works. Exclusions: Final road/footpath surfacing works are excluded from this scope.

Documents

Get these tenders by email

One email a day with new tenders for the trade and area you choose. No account or password needed.

We first email you a link to confirm. Nothing else is sent until you use it. Privacy notice

Quick answers

When is the deadline for this tender?

It closed on 30 October 2026.

How much is this contract worth?

The buyer estimates £1,000,000.

Who is the buyer?

The buyer is Kier Transportation - CP7 NWC.

How many businesses usually bid for a tender like this?

Tenders like this drew about 2.6 bids each (7 awards gave a count). Based on 40 awards in the last 36 months: same trade, same region, similar value. Confidence: good. This describes the past; it does not predict a result.